| 1 |
State |
Telangana |
| 2 |
Name of Project |
Four Laning of NH-161 from Ramsanpally (Design Km 39.980/Existing Km.44.757) to Mangloor (Design Km. 86.788/Existing Km.91.350) (Design Length=46.808kms) in the State Telangana under Bharatmala Pariyojana on Hybrid Annuity Mode. |
| 3 |
Project Type |
Hybrid Annuity Mode (HAM) |
| 4 |
Client |
National Highways Authority of India |
| 5 |
Concessionaire |
KNR Shankerampet Projects Private Limited |
| 6 |
EPC Contractor |
KNR Constructions Limited |
| 7 |
Length of Highway (In Km.) |
46.808 |
| 8 |
Construction Period |
730 Days from Appointed Date |
| 9 |
Concession Period |
730 Days + 15 years from COD |
| 10 |
Date of LOA |
26/03/2018 |
| 11 |
Date of Signing the Agreement |
09/05/2018 |
| 12 |
Appointed Date |
02/05/2019 |
| 13 |
Independent Engineer |
M/S Centro de E studios de Materials, Y Control de obra SA in. With M/s Armenge Engineering and Management Consultant Pvt. Ltd. |